Ohio Statewide Automated Child Welfare Information System (SACWIS)
Document #:  0A1292


Question:   0A1292 Supplement One Page states: the Contractor must also provide an Agile coach for any Agile development processes.

The Agile coach is not listed as a staff position on the Cost Summary. How should we interpret the difference between the statement in Supplement One and the Cost Summary?

Answer:   The Agile coach reference refers to the Scrum Master position in Supplement 1, section 6.7 and the Cost Summary Scrum Master position.

Date: 5/25/2021

Inquiry: 85142


Question:   1. Can an Offeror submit a redlined copy of the Attachment Four: General Terms & Conditions? 2. Will the Offeror have access to Personally Identifiable Information (PII) or Protected Health Information (PHI)? If Offeror will get access to PII, then what type of PII and whether it is sensitive PII (example of sensitive PII would be social security number or date of birth).

Answer:   Part One: The RFP Contract Negotiation section states “An offeror must not submit a Proposal assuming that there will be an opportunity to negotiate any aspect of the Proposal, and any Proposal that is contingent on the State negotiating with the offeror may be rejected.”

Part Two: Ohio SACWIS is a children services information system that contains confidential sensitive information per OAC 5101:2-33-70 | Statewide Automated Child Welfare Information System (SACWIS) access. There is Personally Identifiable Information (PII) housed in the system. The Contractor will have access to PII as a portion of testing and will be required to fill out a personal attestation regarding maintaining confidentiality of the PII.

Date: 5/25/2021

Inquiry: 85114


Question:   Section 4.0 –SACWIS Enhancement - Is it the State’s intention that individual SOWs will be developed jointly between the Contractor and JFS to address the scope of work identified in this section upon contract award? Given that the scoring process for this procurement is a weighted rate card, the cost proposal does not provide a method for Contractors to provide competitive effort estimates for the items identified in this section.

Answer:   Part One: Yes, it is the intention of the State to jointly develop the SOW for SACWIS Enhancements. Part Two: : It is not the intention of the State to include this as part of the cost proposal, rather the State needs to understand how the offeror addressed similar enhancement requests in the past. Please refer to Supplement 1, section 4.2 Evaluation Criteria.

Date: 5/25/2021

Inquiry: 84954


Question:   0A1292 Supplement One Page 6 states: The offeror must have experience working on at least two (2) projects using Informatica Technology and one (1) project using Cognos in the last sixty (60) months. and The offeror must have experience working one (1) or more projects using Cognos version 10 or higher in the last sixty (60) months. Both scored requirements state “one (1) project using Cognos in the last sixty (60) months”. Does this provide more weighting or significance to this experience?

Answer:   Duplicate Question: The State will score based on the response provided and how closely that aligns with the requirements and overall project.

Date: 5/24/2021

Inquiry: 85061


Question:   Resubmitting this inquiry, which was previously submitted on 5/14. 0A1292 Supplement One Page 6 states: The offeror must have experience working on at least two (2) projects using Informatica Technology and one (1) project using Cognos in the last sixty (60) months. and The offeror must have experience working one (1) or more projects using Cognos version 10 or higher in the last sixty (60) months. Both scored requirements state “one (1) project using Cognos in the last sixty (60) months”. Does this provide more weighting or significance to this experience?

Answer:   The State will score based on the response provided and how closely that aligns with the requirements and overall project.

Date: 5/24/2021

Inquiry: 85134


Question:   Resubmitting this inquiry, which was previously submitted on 5/14. 0A1292 RFP General question: Please confirm whether there is any proposal response page limit?

Answer:   Duplicate Question. No page limitation.

Date: 5/24/2021

Inquiry: 85133


Question:   0A1292 RFP General question: Please confirm whether there is any proposal response page limit?

Answer:   No... There is no page response page limit.

Date: 5/24/2021

Inquiry: 85060


Question:   Inquiry: 84861 states: Are you limited to the roles specified in the Rate Card? Answer: No Should respondents add roles to the Rate Card in the submission or will the additional roles be added after award based on need? If the roles should be added to the Rate Card, how will they be weighted and scored?

Answer:   The roles that are specified in the rate card are core roles we require based on the need.

Date: 5/22/2021

Inquiry: 85125


Question:   Amendment 2 - With the posting of Amendment 2 which changed the price sheets and other RFP requirements, will the State consider moving the due date for the vendors to submit their proposals to June 4, 2021?

Answer:   The due date is 6/2/21

Date: 5/22/2021

Inquiry: 85067


Question:   Given that there is just one week between the Inquiry end date 5/17/2021 8:00:00 AM and the Opening Date 5/24/2021. Please consider extending the submission due date (Opening Date) to allow vendors additional time to adequately address the inquiry responses.

Answer:   The inquiry period has expired. The due date is 6/2/21.

Date: 5/22/2021

Inquiry: 85066


Question:   0A1292 RFP Page P 29 states: Each Proposal must contain the following tabbed sections in the response: Technical Proposal 1. Cover Letter 2. Subcontractor Letters 3. Offeror Certification Form 4. Supplier Registration 5. MBE Certification(s) 6. Offeror Profile 7. Proposed Solution – Supplement 1 Response 8. Supplement 2 Response – State IT Policy, Standard and Service Requirements 9. Supplement 3 Response – State Information Security and Privacy Requirements, State Data Handling Requirements 10. Proof of Insurance 11. Payment Address 12. Legal Notice Address 13. W-9 Form 14. Independent Contractor Acknowledgement 15. Affirmation and Disclosure Form 16. Acceptance of Attachment 2: Special Provisions 17. Acceptance of Attachment 4: General Terms and Conditions 18. Assumptions 19. Support Requirements 20. Value-Added Services 21. Acceptance of Supplement 4 - JFS -DAS Security Supplement Addendum The “0A1292 JFS SACWIS Supplement 5 - System Test Standards – final” document was provided and is mentioned on page 5. Should Supplement 5 responses be placed after “Acceptance of Supplement 4” as a tabbed section or within one of the other tabbed sections?

Answer:   Supplement 5 is intended to be for informational purposes - not an acceptance.

Date: 5/22/2021

Inquiry: 85058


Question:   Given that an amendment is forthcoming, please consider extending the Inquiry end date to allow vendors additional time to adequately review the amendment.

Answer:   The inquiry period has expired. The due date is 6/2/21.

Date: 5/22/2021

Inquiry: 85024


Question:   Given that the State is working on an amendment that may have a material impact on the RFP requirements, would the State please consider extending the due date by two weeks to provide time for vendors to make any necessary adjustments and submit compliant and responsive proposals?

Answer:   The inquiry period has expired. The due date is 6/2/21.

Date: 5/22/2021

Inquiry: 85008


Question:   For the 1st Mandatory Requirement: Can the State confirm that when they stated “Additionally, the prime contractor must provide 50% of the staffing towards each Statement of Work and/or Deliverables” that this means that the proposed offeror must have provided at least 50% of the staffing as the prime contractor for the 2 public sector projects that they submitted to meet this mandatory requirement.

Answer:   The prime contractor must provide 50% of the staffing towards each Statement of Work and/or Deliverables.

Date: 5/22/2021

Inquiry: 85007


Question:   Can the State please confirm that the prime contractor needs to provide evidence of experience serving as a prime contractor where it has provided at least 50 percent of the staff for at least 2 successfully completed public sector projects of similar size and scope within the area of child welfare services?

Answer:   Duplicate. Answered on inquiry 85005

Date: 5/22/2021

Inquiry: 85006


Question:   Can the State please confirm that the prime contractor needs to provide evidence of its experience serving as a prime contractor where it has successfully completed at least 2 public sector projects of similar size and scope within the area of child welfare services?

Answer:   The prime contractor needs to provide evidence of its experience serving as a prime contractor where it has successfully completed at least 2 public sector projects of similar size and scope.

Date: 5/22/2021

Inquiry: 85005


Question:   In the States responses to inquiries 84934, 84790, and 83746 the State indicates that an addendum to the RFP requirements will be posted. Will the State consider extending the due date for the RFP responses by two weeks to June 7, 2021?

Answer:   Inquiry period has expired. The due date is 6/2/21

Date: 5/22/2021

Inquiry: 84996


Question:   Section 1.4 of Supplement 1 (page 4) includes mandatory qualifications that we interpret to be conflicting. Bullet (a) says “The offeror must demonstrate experience working on at least two (2) projects using JAVA, WebSphere, and Unix and one (1) project using an Oracle relational database within the last sixty (60) months. Bullet (b) says “The offeror must demonstrate they have successfully implemented at least three (3) projects that included at least one (1) project from development through implementation using JAVA, WebSphere, and Unix within the last sixty (60) months.” We request that the State please clarify the requirements for these mandatory qualifications.

Answer:   This was corrected with Amendment 1

Date: 5/22/2021

Inquiry: 84986


Question:   Page 47 of the RFP – Software Warranty defines the obligation of the Contractor to provide warranty services for 12 months beyond date of acceptance of deliverables, defining the end of services to be provided under this contract. Supplement 1, Section 4.3, bullet h) refers to Contractor ‘help desk’ obligations beyond the end of the contractual Warranty period. Can the State provide the specific length of time the Contractor is expected to provide ‘help desk’ support beyond the contractual warranty period, and if not, would the State be amenable to modifying the Software Warranty RFP requirements on page 47 accordingly, to accommodate the State’s additional warranty obligations associated with this Contract (if any)?

Answer:   Support is required throughout the contract period. Vendor expected to help support the help desk by researching technical items that come to the help desk and data fixes when needed.

Date: 5/22/2021

Inquiry: 84952


Question:   Resubmitting this inquiry, which was previously submitted on 5/14. 0A1292 RFP Page P 29 states: Each Proposal must contain the following tabbed sections in the response: Technical Proposal 1. Cover Letter 2. Subcontractor Letters 3. Offeror Certification Form 4. Supplier Registration 5. MBE Certification(s) 6. Offeror Profile 7. Proposed Solution – Supplement 1 Response 8. Supplement 2 Response – State IT Policy, Standard and Service Requirements 9. Supplement 3 Response – State Information Security and Privacy Requirements, State Data Handling Requirements 10. Proof of Insurance 11. Payment Address 12. Legal Notice Address 13. W-9 Form 14. Independent Contractor Acknowledgement 15. Affirmation and Disclosure Form 16. Acceptance of Attachment 2: Special Provisions 17. Acceptance of Attachment 4: General Terms and Conditions 18. Assumptions 19. Support Requirements 20. Value-Added Services 21. Acceptance of Supplement 4 - JFS -DAS Security Supplement Addendum The “0A1292 JFS SACWIS Supplement 5 - System Test Standards – final” document was provided and is mentioned on page 5. Should Supplement 5 responses be placed after “Acceptance of Supplement 4” as a tabbed section or within one of the other tabbed sections?

Answer:   Supplement 5 is intended to be for information standards reference only - not an acceptance.

Date: 5/21/2021

Inquiry: 85131


Question:   Inquiry: 84861 states: Does a subcontractor need to have a business office location in Ohio to be qualified as a vendor? Answer: Yes Do non-Ohio certified MBE subcontractors need to have an office location in Ohio? Is registration of non-Ohio certified MBE subcontractors to do business in Ohio sufficient? Is it acceptable for a non-Ohio certified MBE subcontractor to register to do business in Ohio after award and before the start of any Work?

Answer:   Duplicate Question. Answered on 85130

Date: 5/21/2021

Inquiry: 85056


Question:   Resubmitting this inquiry, which was previously submitted on 5/14. Inquiry: 84861 states: Does a subcontractor need to have a business office location in Ohio to be qualified as a vendor? Answer: Yes Do non-Ohio certified MBE subcontractors need to have an office location in Ohio? Is registration of non-Ohio certified MBE subcontractors to do business in Ohio sufficient? Is it acceptable for a non-MBE subcontractor to register to do business in Ohio after award and prior to the start of any Work?

Answer:   Inquiry: 84861 states: Does a subcontractor need to have a business office location in Ohio to be qualified as a vendor? Answer: [No. Only proposed MBE vendors and/or subcontractors need to have an office location in Ohio.]

Do non-Ohio certified MBE subcontractors need to have an office location in Ohio? Answer: [No]

Is registration of non-Ohio certified MBE subcontractors to do business in Ohio sufficient? Answer [Yes]

Is it acceptable for a non-Ohio certified MBE subcontractor to register to do business in Ohio after award and before the start of any Work? [Yes this is acceptable, but may delay the award process. Additionally, to be considered for MBE credit, all subcontractors must be registered to do business with the State of Ohio and certified as a Minority Business Enterprise. MBE vendors that do not reside in Ohio will not count towards MBE credit.]

Date: 5/21/2021

Inquiry: 85130


Question:   0A1292 RFP P. 57 Includes the following question in the Offeror Profile: Acknowledgement the prime contractor will provide 50% of the staffing towards each Statement of Work and/or Deliverables: Yes or No If the subcontractor is completing this profile, should they work with prime to answer these questions on behalf of the prime?

Answer:   Duplicate Question. Answered on 85321

Date: 5/21/2021

Inquiry: 85059


Question:   Resubmitting this inquiry, which was previously submitted on 5/14. 0A1292 RFP P. 57 Includes the following question in the Offeror Profile: Acknowledgement the prime contractor will provide 50% of the staffing towards each Statement of Work and/or Deliverables: Yes or No If the subcontractor is completing this profile, should they work with prime to answer these questions on behalf of the prime?

Answer:   "The prime contractor must provide 50% of the staffing towards each Statement of Work and/or Deliverables."

If the subcontractor is completing this profile, should they work with prime to answer these questions on behalf of the prime? Yes.

Date: 5/21/2021

Inquiry: 85132


Question:   0A1292 RFP Page 17 states: The “Weight” for the first two Mandatory Scored Requirements are blank. Was this intended or should there be a “Weight” value?

Answer:   The weight values have been added to the most recent published amendment.

Date: 5/21/2021

Inquiry: 85057


Question:   Given the time between the Inquiry end date 5/21/2021 8:00:00 AM and the Opening Date 6/2/2021. Please extend the inquiry end date and submission due date (Opening Date) to allow vendors time to adequately address the inquiry responses.

Answer:   At this time we are not looking to extend the inquiry date beyond 05/21/21.

Date: 5/21/2021

Inquiry: 85140


Question:   Please clarify which amendment addresses Inquiry: 84934 and clarifies the MBE set-aside points. Specifically, If the Primary Offeror is also a State of Ohio Certified MBE, for scoring purposes will the percentage completed by the Primary Offeror be added to the MBE sub percentage for Total Project cost allocation?

Answer:   No, the percentage of work completed by the Primary Offeror will not count towards the MBE sub percentage for Total Project cost allocation. Only the percentage for work subcontracted to MBE vendors will count.

Date: 5/21/2021

Inquiry: 85139


Question:   0A1292 Supplement One Page 20 states: “Ohio Eligibility Systems applications” experience is a desired requirement for the Testing Analyst 2. Please confirm this is a desired requirement for the Testing Analyst 2.

Answer:   Duplicate Question. Answered on 85136

Date: 5/21/2021

Inquiry: 85063


Question:   Resubmitting this inquiry, which was previously submitted on 5/14. 0A1292 Supplement One Page 20 states: “Ohio Eligibility Systems applications” experience is a desired requirement for the Testing Analyst 2. Please confirm this is a desired requirement for the Testing Analyst 2.

Answer:   Testing Analyst 2 candidates who have "Ohio Eligibility Systems applications" Is preferable.

Date: 5/21/2021

Inquiry: 85136


Question:   0A1292 Supplement One Page 28 states: “Child Support Enforcement system” experience is a desired requirement for Business Analyst 2. Please confirm this is a desired requirement for the Business Analyst 2.

Answer:   Duplicate Question. Answered on 85135

Date: 5/21/2021

Inquiry: 85065


Question:   Resubmitting this inquiry, which was previously submitted on 5/14. 0A1292 Supplement One Page 28 states: “Child Support Enforcement system” experience is a desired requirement for Business Analyst 2. Please confirm this is a desired requirement for the Business Analyst 2.

Answer:   "Child Support Enforcement System" experience is a desired requirement but not mandatory for Business Analyst 2 position.

Date: 5/21/2021

Inquiry: 85138


Question:   0A1292 Supplement One Page 20 states: An Associates Degree in Computer Science is a Desirable requirement for the Business Analyst/Testing Lead. Many of the Programmer positions only desire an “Associates Degree or higher”. Please confirm “Computer Science” is a desired requirement for the Business Analyst/Testing Lead.

Answer:   Duplicate Question. Answered on 85137

Date: 5/21/2021

Inquiry: 85064


Question:   0A1292 Supplement One Page 12 states: The Contractor ‘help desk’ support is required after the warranty period in the event there is an issue identified in the code developed by the Contractor in production at no additional cost to State. When will the required Contractor ‘help desk’ support after the warranty period conclude?

Answer:   Duplicate. Answered on 85135

Date: 5/21/2021

Inquiry: 85062


Question:   Resubmitting this inquiry, which was previously submitted on 5/14. 0A1292 Supplement One Page 20 states: An Associates Degree in Computer Science is a Desirable requirement for the Business Analyst/Testing Lead. Many of the Programmer positions only desire an “Associates Degree or higher”. Please confirm “Computer Science” is a desired requirement for the Business Analyst/Testing Lead.

Answer:   "Associates Degree or higher" can accepted for BA and Testing lead positions.

Date: 5/21/2021

Inquiry: 85137


Question:   Resubmitting this inquiry, which was previously submitted on 5/14. 0A1292 Supplement One Page 12 states: The Contractor ‘help desk’ support is required after the warranty period in the event there is an issue identified in the code developed by the Contractor in production at no additional cost to State. When will the required Contractor ‘help desk’ support after the warranty period conclude?

Answer:   Throughout the contract period. Vendor is expected to help support the help desk by researching technical items that come to the help desk and data fixes when needed.

Date: 5/21/2021

Inquiry: 85135


Question:   Given an amendment will be forthcoming for further clarification to address submitted inquiries and the Inquiry end date 5/21/2021 8:00:00 AM is less than 24 hours, please extend the Inquiry end date to allow vendors enough time to adequately understand the inquiry responses.

Answer:   The amendment was posted on 5/18/21. The inquiry date was extended to 5/21/21 and the opening date is now scheduled for 6/2/21

Date: 5/20/2021

Inquiry: 85123


Question:   OA1292 JFS SACWIS Cost Summary document: Given that peak staffing totals are not considered in the Cost Evaluation totals, how should vendors represent MBE costs where more than one MBE resource is proposed for a given role? (e.g.: The MBE provides 3 programmer analyst 3 roles, however, the weighted evaluation total would only represent 1 FTE being provided by the MBE per the scoring instructions)

Answer:   An amendment will be forthcoming for further clarification.

Date: 5/14/2021

Inquiry: 85003


Question:   • Currently there is only one project manager identified to manage all projects. Is this optimal based on the number of identified enhancements and/or will roles be addressed via change order? • Regarding the mix of roles defined in rate card, is this all inclusive of the roles for RFP Response? • Are you limited to the roles specified in the Rate Card? • Based on statement that the Award winner will be offered all or part of the work: Could the RFP be awarded to multiple companies? • Are Senior Technical Leaders really technical managers, not necessarily project managers? They are asked to be involved in PM activities, but not manage the projects. • Does a subcontractor need to have a business office location in Ohio to be qualified as a vendor?

Answer:   Currently there is only one project manager identified to manage all projects. Is this optimal based on the number of identified enhancements and/or will roles be addressed via change order? Answer: Yes (1) Project Manager to manage the Projects

Regarding the mix of roles defined in rate card, is this all inclusive of the roles for RFP Response? Answer: Yes

Are you limited to the roles specified in the Rate Card? Answer: No

Based on statement that the Award winner will be offered all or part of the work: Could the RFP be awarded to multiple companies? Answer: The RFP will be awarded to one vendor.

Are Senior Technical Leaders really technical managers, not necessarily project managers? They are asked to be involved in PM activities, but not manage the projects. Answer: Technical leaders are not expecting to manage the projects.

Does a subcontractor need to have a business office location in Ohio to be qualified as a vendor? Answer: Yes

Date: 5/13/2021

Inquiry: 84861


Question:   With regards to the first mandatory requirement: "The offeror or its proposed subcontractor must demonstrate experience within the last sixty (60) months providing IT technical support and project management services for at least two (2) public sector projects of similar size and scope worked in the area of child welfare services." Would adjacent services like WIC, SNAP, or TANF experience be accepted within the "area of child welfare services?"

Answer:   WIC, SNAP and TANF are Family Assistance programs and not under the scope of Children Services/Child Welfare.

Date: 5/12/2021

Inquiry: 84949


Question:   Please confirm: If the Primary Offeror is also a State of Ohio Certified MBE, for scoring purposes will the percentage completed by the Primary Offeror be added to the MBE sub percentage for Total Project cost allocation?

Answer:   An amendment will be forthcoming to further clarify the MBE set-aside points.

Date: 5/12/2021

Inquiry: 84934


Question:   Attachment Eight Affirmation and Disclosure Form RFP page 70 Location where state data will be located, by Contractor: Name/Location(s) where state data will be located by subcontractor(s): Attachment Eight, Affirmation and Disclosure Form asks Offerors to answer: Location where state data will be located, by Contractor and Name/Location(s) where state data will be located by subcontractor(s):. It is our understanding that state data will be stored by ODJFS. Please clarify that is the case. If so, please advise how vendors should answer these questions."

Answer:   If the offeror will not be storing data, the response can indicate no state data will be stored by the Contractor or subcontractor, if applicable.

Date: 5/12/2021

Inquiry: 84795


Question:   Supplement One, Section 6.0 p.15 states: "since the technical requirement is provided at the top of the page regardless of whether it is on the same or different pages of the form" This language seems to suggest there is a form the offeror needs to complete the candidate profile. Is that correct? If so. is the form available within the RFP documents?

Answer:   An amendment will be forthcoming to remove the form reference.

Date: 5/12/2021

Inquiry: 84790


Question:   We are requesting clarifications be provided for Supplement 1 - Section 6.0: Key Personnel A. IV: • For the key candidate references, does the “technical requirement” (provided at the top of the page) refer to each role’s description listed after the header? • To clarify, the resume must include details to support the requirements and desirable requirements for each position with the candidate’s appropriate qualifications and work experience? • Also, if a candidate will be proposed for multiple positions, then the work experience must be listed again for each position? • In addition, is the form mentioned a separate document or the resume included in the submitted RFP?

Answer:   For the key candidate references, does the "technical requirement" (provided at the top of the page) refer to each role's description listed after the header? Answer: Yes

To clarify, the resume must include details to support the requirements and desirable requirements for each position with the candidate's appropriate qualifications and work experience? Answer: Yes

Also, if a candidate will be proposed for multiple positions, then the work experience must be listed again for each position? Answer: Yes

In addition, is the form mentioned a separate document or the resume included in the submitted RFP? Answer: We are seeking resumes for each key positions.

Date: 5/12/2021

Inquiry: 84771


Question:   Cost Summary The Cost Summary spreadsheet list thirty (30) positions. Will each of these positions be full time (2000 hours annually) for the duration of the contract? If not, can the State please provide an estimated number of hours each role will be used? Will the State be multiplying the expected number of hours to be used annually for evaluation purposes? If not, can the State please explain how the rates will be evaluated.

Answer:   An amendment will be forthcoming to clarify this question.

Date: 5/12/2021

Inquiry: 83746


Question:   Supplement 1 - Section 3.0 - General Scope of Work p.8, bullets c and k refer to activities required by the Contractor to support the State’s SACWIS Help Desk. Section 4.3 SACWIS Enhancements (page 11, bullets g and h) refer to obligations of the Contractors ‘help desk’ staff. Can the State elaborate on the difference between the required commitment for the Contractor to support the SACWIS Help Desk vs. the ‘help desk’ duties expected to be performed directly by the Contractor? Specifically, what activities are required over and above the obligations to support the SACWIS Help Desk in fulfilling the requirements for the Contractor ‘help desk’ defined in Section 4.3?

Answer:   Section 3.0 refers to the general scope of work within the office and what will be supported by the contractor. The Ohio SACWIS Help Desk currently consists of 5 staff who receive functional and data fix issues from agency system users by phone, fax and email. The contract resources provide support for resolution of the issues that come in from agency users. The expectation is for the vendor to provide assistance to resolve issues within the Production support and warranty maintenance period. Section 4.3 refers to the different phases of the Ohio SACWIS Enhancement cycle and the contractors responsibilities in each cycle (which overlaps the help desk assistance in section 3).

Date: 5/11/2021

Inquiry: 84951


Question:   The State references "statement of work" multiple times in Supplement 1, and does not reference the IDA process typically used throughout Ohio Agencies. Can contractors assume that Statements of Work will be the vehicle managing the allocation and performance of work associated with this Contract going forward (as opposed to the IDA process)?

Answer:   That is correct.

Date: 5/11/2021

Inquiry: 84953


Question:   Supplement One, Section 6.a pages 14-15 states: "The offeror must provide a client contact name, title, phone number, email address, company name, and mailing address. The offeror also must include the same information for an alternate client contact in case the State cannot reach the primary contact. Failure to provide this information or providing information that is inaccurate or out of date may result in the State not including the reference in the evaluation process or rejecting the offeror’s Proposal. The contact information given must be for a person within the client’s organization and not a co-worker or a contact within the offeror’s organization, subsidiaries, partnerships, etc." Question: Some proposed personnel may exceed the required qualifications but may not necessarily have client-facing experience. In these cases, will the State accept references from individuals from outside the clients organization? Such as former coworker or manager? In cases where proposed candidates have not had client-facing interaction and have been with the Offeror organization for more than five years, will the State accept references from within the offerors organization?

Answer:   This requirement refers to ' Key personal, Supplement one ' listed on page #18 of the RFP document. Further, as stated in page 14-15 of the Section 6 of the supplement one document, these key positions require client references as requested.

Date: 5/10/2021

Inquiry: 84839


Question:   Cost Summary The Cost Summary spreadsheet list thirty (30) positions. Will each of these positions be full time (2000 hours annually) for the duration of the contract? If not, can the State please provide an estimated number of hours each role will be used?

Answer:   NO. The 7 key positions are required to be fulltime(2000 hours annually) for the duration of the contract. Rest of the positions will be required depend on scope of work define in individuals statement of work (SOW).

Date: 5/10/2021

Inquiry: 84791


Question:   RFP Document Section 1.4. Sheltered MBE Solicitation/Embedded MBE Set-Aside. Page 8 If the vendor uses an Ohio Certified WBE (Woman owned) or Ohio Certified VBE (Veteran Owned) business as one of its subcontractors will the State count this spend towards the requirement contained in Section 1.4.

Answer:   The response is no. Although the state encourages the use of WBE and VBE firms, those entities will not satisfy the MBE requirements in the RFP.

Using an Ohio Certified WBE (Woman owned) or Ohio Certified VBE (Veteran Owned) business would not count towards the requirements for embedded solicitation. Subcontractors must be Ohio certified MBE vendors. The subcontractors can have dual or multiple designations but must have the MBE certification for the participation to count (for example a vendor can be a veteran-owned MBE or woman-owned MBE).

Date: 5/10/2021

Inquiry: 84881


Question:   RFP Attachment Three 13. W-9 Form p. 31 The offeror must complete a W-9 form in its entirety. The offeror must submit at least one originally signed W-9. All other copies of a Proposal may contain copies of the W-9. The offeror must indicate on the outside of the binder which Proposal contains the originally signed W-9. "The description for Tab 13 states: ""The offeror must submit at least one originally signed W-9... The offeror must indicate on the outside of the binder which Proposal contains the originally signed W-9."" Question: Will the State accept electronic signatures in lieu of "wet" signatures and amend the requirement for marking the outside of the technical binder, given the logistical challenges caused by current COVID closures and restrictions in place due to the coronavirus pandemic?

Answer:   An electronic signature solution will be permitted for the signature.

Date: 5/7/2021

Inquiry: 84792


Question:   At this point, would the State consider extending the submission due date by two weeks to allow vendors additional time to further refine their proposals in order to provide the State with higher quality responses?

Answer:   At this time, JFS is not seeking to extend the submission date.

Date: 5/7/2021

Inquiry: 84884


Question:   Part TWO, page 35 of the PDF RFP: The State indicates there may be other vendors contracted to support work for this project in the future, in particular, an IV&V vendor. 1. Does the State already have an IV&V vendor contracted to engage on this scope of work for the project? 2. If the State does not have a vendor contracted for this work, can the State indicate when that vendor is anticipated to be procured?

Answer:   1) No

2) As such, the State is not looking to procure an IV&V vendor at this time. Certain conditions have to be met for this work to be initiated. For more information, please visit the 'United States Code of Federal regulations ( CFR) Title 45" , by visiting this link - https://www.govregs.com/regulations/title45_chapterA_part95_subpartF_subjgrp54_section95.626

Date: 5/5/2021

Inquiry: 84780


Question:   Re: inquiry 84781, the State has clarified that named individuals, profiles, and references are required for the 7 key personnel candidates listed in RFP Attachment 1. Will the State please clarify what is required to be submitted for the remaining 18 key personnel?

Answer:   Vendors are required to submit the rate in the Cost summary sheet.

Date: 5/5/2021

Inquiry: 84836


Question:   RFP Attachment Three p. 28 The RFP states: "To aid Offerors in the creation of the most favorable depiction of their responses, alternative formats are acceptable that use typefaces, styles or shaded backgrounds, so long as the use of these formats are consistent (font size 10) throughout the Offeror’s response and readily distinguishable from the baseline RFP." Question: Are offerors required to use font size 10 for their response format? And if so, may offerors use a larger size font for section headings and subheadings?"

Answer:   Proposals cannot go below 10pt but you are welcome to use larger if you like.

Date: 5/5/2021

Inquiry: 84794


Question:   RFP Part Three p. 7 states: The package with the technical section of the Proposal must be sealed and contain one (1) originally signed technical section and seven (7) additional copies of the technical section Question: Does the State consider and would it accept electronic signature using the docusign or similar application as "originally signed" for the purposes of the original technical proposal?

Answer:   The original must be a wet signature

Date: 5/5/2021

Inquiry: 84793


Question:   0A1292 Supplement One Page 10 states: Tiered Treatment Foster Care - Create a tiered program for caseworkers to help expand career pathways in children services. Create expanded career pathway programs that empower children services caseworkers to continue learning and growing in their profession. The description does not appear to match the title. Please clarify whether the proposal should respond to one or both topics. Any clarification is appreciated.

Answer:   The Tiered Treatment Foster Care narrative comes from the Children Services Transformation final report. If the vendor would like additional information on the subject, they may review the full report at

https://governor.ohio.gov/wps/portal/gov/governor/media/news-and-media/children-services-transformation-final-report-11202020

Date: 5/5/2021

Inquiry: 84824


Question:   Page 18 of the RFP (Attachment One - Evaluation Criteria) identifies seven key personnel in the scored requirements. Section 6 of Supplement One refers to a total of 25 Key Personnel in Section 6.0 and requests profiles for each of the 25 Key personnel. To clarify, is the State requesting that vendors provide named individuals, profiles, and references for all 25 roles identified in Section 6.0 of Supplement 1 (Key Personnel), or is it the State’s intent for vendors to use the descriptions provided in Section 6.0 to complete the applicable profiles for the 7 Key (scored) Personnel candidates listed in RFP Attachment 1: Scoring Criteria?

Answer:   The State is requesting that vendors must provide named individuals, profiles, and references for the 7 key personnel candidates listed in RFP Attachment 1.

Date: 5/3/2021

Inquiry: 84781


Question:   RFP Attachment Six p. 55 #5 states "The offeror certifies that it’s regular, full-time employees will perform at least 30% of the Work." The RFP Cost Summary states that "The prime contractor must provide 50% of the staffing towards each Statement of Work and/or Deliverables." Please clarify what percentage is expected from the Offeror/Prime Contractor."

Answer:   An Amendment is being drafted to cover this question.

Date: 4/30/2021

Inquiry: 83744


Question:   RFP Attachment One: Evaluation Criteria p. 18 "The evaluation criteria table in RFP Attachment One includes seven key personnel roles: - Senior Project Manager, Section 6.1 - Technical Project Leader, Section 6.2 - Senior Business Intelligence ETL Developer, Section 6.3 - Senior Business Intelligence Report Developer, Section 6.4 - Testing Analyst 2, Section 6.5 - Business Analyst/Testing Lead, Section 6.6 - Programmer Analyst 3, Section 6.21 Some of these roles, such as the Technical Project Leader, contain peak staffing numbers greater than one (1), please confirm that the vendors only need to submit one resume for each role.

Answer:   Vendors only need to submit their best resume for each role. JFS is requesting to submit one for each position.

Date: 4/30/2021

Inquiry: 83747


Question:   Is the State of Ohio willing to negotiate a cap on the unlimited liability clause on the sample contract? If vendors suggest changes to the standard contract terms will they be disqualified?

Answer:   The RFP Sample Contract in Attachment Five does not have a unlimited liability clause. Please refer to the RFP "Limitation of Liability" section in Attachment 4, page 48.

An offeror must not submit a Proposal assuming that there will be an opportunity to negotiate any aspect of the Proposal, and any Proposal that is contingent on the State negotiating with the offeror may be rejected. Please refer to the RFP "Contract Negotiations" section, page 13.

Date: 4/30/2021

Inquiry: 83700


Question:   May JFS provide potential respondents with a copy of the incumbents (CGIs) current contract for the SACWIS support and all associated pricing and SOWs.

Answer:   No. The scope and deliverables are different than the existing contract.

Date: 4/28/2021

Inquiry: 83719


Question:   The procurement page shows this bid as a MBE set-aside under the Procurement Programs category. The actual RFP document states that this is an open-market bid, with a 15% MBE Annual Goal. Will the State please confirm this is an open-market bid, with a 15% MBE annual goal?

Answer:   Duplicate Question. Answered on Inquiry 83727

Date: 4/28/2021

Inquiry: 83728


Question:   Would the State consider a two-week extension to the due date?

Answer:   The State is not looking to extend at this time.

Date: 4/28/2021

Inquiry: 83729


Question:   Can commercial client’s references be used to fulfill the RFP references requirements?

Answer:   It does not apply to every requirement. It depends on the specific item you are trying to meet. We would accept commercial experience for the following and similar requirements. "The offeror or its proposed subcontractor must have at least two (2) projects with API management experience that includes creating, maintaining and publishing API’s in the last thirty-six (36) months."

Date: 4/28/2021

Inquiry: 83701


Question:   The procurement page shows this bid as a MBE set-aside under the Procurement Programs category. The actual RFP document states that this is an open-market bid, with a 15% MBE Annual Goal. Will the State please confirm this is an open-market bid, with a 15% MBE annual goal?

Answer:   Yes, this is open-market with potential for additional points if the offeror meets the MBE component.

Date: 4/28/2021

Inquiry: 83727


Question:   Due to the complexity of the solution, we would like to respectfully request that RFP response due date is extended to June 28th, 2021, at 5 PM EDT?

Answer:   JFS is not looking to extend at this time.

Date: 4/27/2021

Inquiry: 83697


Question:   Are there any restrictions on using project resources based in Global Delivery Centers outside of the United States?

Answer:   Yes, there are restrictions. Please check the Executive Order that addresses Offshore services and data. Refer to Executive Order 2019- 12D https://governor.ohio.gov/wps/portal/gov/governor/media/executive-orders/2019-12d

Date: 4/27/2021

Inquiry: 83698


Question:   RFP Page 18: Key Personnel: Is there a particular format the State requires to display the reference, education & training, and qualification information for each of the key personnel noted in the Evaluation Criteria? In the past, the State has provided forms to support responding to these requirements, but no such forms appear to be provided in the RFP or in Supplement 1.

Answer:   Supplement 1, section 6.0 provides the documentation required for the Key Personnel. There is not a specific form in the RFP or Supplement one required to provide this information.

Date: 4/27/2021

Inquiry: 83695


Question:   Regarding inquiry 83613, does the submitting firm need to have the experience or could one of their subs have extensive experience? In short, is the mandatory requirement met if a sub on the pursuit has child welfare experience?

Answer:   Submitting firm or their Sub must have experience in Child welfare.

Date: 4/26/2021

Inquiry: 83667


Question:   Under the Mandatory Requirements Section it States the following: "The offeror or its proposed subcontractor must demonstrate experience within the last sixty (60) months providing IT technical support and project management services for at least two (2) public sector projects of similar size and scope worked in the area of child welfare services. For the purpose of this RFP a system of ‘similar size and scope’ is defined as a large transaction processing system with both an on-line data entry interface and a web-based interface with a minimum of 6,000 authorized users." If an offeror can meet the second section of the paragraph, but not within the area of child welfare services will they be excluded? This offeror has experience in large transaction intensive public sector system implementations and modernizations, but not in the area of child welfare services.

Answer:   No. Some form of child welfare experience is expected. If there is no child welfare experience, proposals will be excluded.

Date: 4/23/2021

Inquiry: 83613


Question:   1. Is there an incumbent on this project currently ? If so what is the name of the firm?. 2. Will you be providing us with the names of other interested offerors in case we seek partnering opportunities? 3. Will there be a bid conference (Teams or zoom conference) to clarify project requirements?

Answer:   1) CGI 2) No 3) No

Date: 4/22/2021

Inquiry: 83604