Question:   Given that the responses to some of our questions will significantly impact the solution we intend to propose, would the State be willing to grant an extension to the proposal due date by two weeks (i.e., to October 19)?

Answer:   The State is not currently considering an extension at this time.

Date: 9/25/2020

Inquiry: 79282


Question:   Would the State be willing to grant an extension to the Inquiry period?

Answer:   The State is not currently considering an extension at this time.

Date: 9/25/2020

Inquiry: 79281


Question:   Does PUCO have existing automated integration tests that can be used to verify the solution?

Answer:   No, PUCO does not today have automated regression tests for this software.

Date: 9/25/2020

Inquiry: 79286


Question:   In the interest of submitting the most accurate proposal response possible, would it be possible to obtain the source code for the DIS application and supporting interfaces?

Answer:   Unfortunately, we are unable to support making the source code available prior to contract award.

Date: 9/25/2020

Inquiry: 79285


Question:   Are there any known gaps between the DIS desktop and web-based applications and the State of Ohio security standards referenced in Supplement 3 to the RFP?

Answer:   The platform software upgrade is in part driven by concerns about security and having some hardware and software out of maintenance from the supplier.

Date: 9/25/2020

Inquiry: 79284


Question:   Would PUCO be open to migrating the DIS desktop application to a web-based application?

Answer:   This is not expected in the initial delivery unless it emerges as the least cost way to get the desktop application to fully supported platform software.

Date: 9/25/2020

Inquiry: 79283


Question:   Is there an expectation to leverage State of Ohio IT services referenced in Supplement 2 as much as possible?

Answer:   Yes, the PUCO follows enterprise specified standards whenever possible.

Date: 9/25/2020

Inquiry: 79280


Question:   For DevOps implementation, is there an expectation to migrate the workstream or start the workstream managment for this project within Azure DevOps?

Answer:   No workstream migration expected. The State expects to start the workstream management for this project in ADO.

Date: 9/25/2020

Inquiry: 79279


Question:   What is PUCOs existing source code repository and workstream management platform?

Answer:   Currently, PUCO uses TFP and VSS for source code repository. No workstream management platform is in use.

Date: 9/25/2020

Inquiry: 79278


Question:   Is there an eCommerce component to DIS? For example, Is there any filing fee for dockets if so, does PUCO accept ACH payments?

Answer:   No, there are no filing fees or other fiscal transactions associated with the DIS system.

Date: 9/25/2020

Inquiry: 79277


Question:   Does the Azure DevOps implementation only include source code for the DIS application or for all PUCO applications?

Answer:   The Azure DevOps deliverable is to get the DIS application into the Azure DevOps.

Date: 9/25/2020

Inquiry: 79276


Question:   Is upgrading SQL server upgrade to SS 2019 and IBM Content Manager to 8.6 in scope for the expected upgrade for DIS?

Answer:   The SQL upgrade will be done in house by existing staff. The Content Manager upgrade is in scope for this RFP initial delivery.

Date: 9/25/2020

Inquiry: 79275


Question:   Does DIS (or any of the other apps on this platform) contain PHI/PII that may be subject to a BAA or other similar contractual control mechanism?

Answer:   DIS does not contain PII, PHI. There are sometimes files containing confidential and/or trade secret data that are submitted to DIS on applications or cases. These confidential documents need to have special handling to ensure only appropriate accessibility.

Date: 9/25/2020

Inquiry: 79274


Question:   Will PUCO be able to provide more specific information about the applications listed on p. 102 of the RFP?

Answer:   Yes, the historic design and development artifacts will be made available to the awarded vendor.

Date: 9/25/2020

Inquiry: 79273


Question:   Who currently supports the applications listed on p. 102 of the RFP? Is it an internal group or is this contracted to a third-party vendor?

Answer:   These applications are supported by internal state and T&M staff.

Date: 9/25/2020

Inquiry: 79272


Question:   Will the contractors work also require an upgrade from SSL to TLS?

Answer:   No, the State does not expect such an upgrade.

Date: 9/25/2020

Inquiry: 79271


Question:   Microsoft has announced they are no longer adding functionality to the VB language. Is the expectation to retain your existing source code and fix any breaking changes due to the framework upgrade or to rewrite the applications to the latest version of the .NET language using C#?

Answer:   Our intent for the effort in this RFP is to bring the existing code to current platform revision levels and address any outages caused by that upgrade.

Date: 9/21/2020

Inquiry: 79270


Question:   OFFEROR MANDATORY REQUIREMENT #1 - Application experience as a Contractor providing development services for at least two (2) large, complex legacy .Net systems or the development of new .Net systems on projects similar in size and scope. One of the referenced projects needs to be support of a docketing function for a legal department. Each reference must be for an operational production system that lasted a minimum of twenty-four (24) consecutive months. Reference "One of the referenced projects needs to be support of a docketing function for a legal department."

Is this a soft or hard requirement? We do not have experience supporting a docketing function for a legal department.

Answer:   Revised response: The flow of documents is the life blood of the PUCO. An appropriate reference project that will fulfill these docketing requirements needs to be a system that flawlessly accepts, processes, stores, and makes accessible documents between departments and teams both within and external to the enterprise. The reference system must handle documents that range in size from small to over 50 Mb and securely handle files that include trade secret and confidential information. The reference system must be of the caliber to stand up to the reliability and dependability of systems that handle legal proceeding and decisions while still being straightforward enough to support new users seamlessly. This requirement is mandatory and must be fulfilled by either the Offeror or Subcontractor.

Original response: This requirement is mandatory and must be fulfilled by either the Offeror or Subcontractor.

Date: 9/18/2020

Inquiry: 79261


Question:   Does PUCO currently have any applications deployed in Azure cloud environment or in development stage in Azure cloud either by internal IT staff or through staff augmentation / outside vendor. ? If outside vendor is involved in Azure development can you pls share vendor details.

Answer:   The current staff at the PUCO has completed a Proof of Concept activity sponsored by Micro Soft, working with 10th Magnitude (MS' subcontractor) to move 5 applications to the Azure cloud. Although we had some successes, there is an authentication problem that we are working before any of the applications can be deployed to production.

Date: 9/18/2020

Inquiry: 79267


Question:   If prime vendor is MBE, do we qualify for 10% MBE Set-aside or we have to still include another MBE vendor for MBE Set-aside?

Answer:   The prime vendor is not eligible to qualify. Ohio certified MBE subcontractors must be competitively selected by the Prime according to Requirements for Embedded Solicitation (RFP, Page 3).

Date: 9/14/2020

Inquiry: 79254


Question:   For the Mandatory Requirement 1: Application experience as a Contractor providing development services for at least two (2) large, complex legacy .Net systems or the development of new .Net systems on projects similar in size and scope. One of the referenced projects needs to be support of a docketing function for a legal department. Each reference must be for an operational production system that lasted a minimum of twenty-four (24) consecutive months. Could you please clarify in details about "referenced projects needs to be support of a docketing function for a legal department"

Answer:   The flow of documents is the life blood of the PUCO. An appropriate reference project that will fulfill these docketing requirements needs to be a system that flawlessly accepts, processes, stores, and makes accessible documents between departments and teams both within and external to the enterprise. The reference system must handle documents that range in size from small to over 50 Mb and securely handle files that include trade secret and confidential information. The reference system must be of the caliber to stand up to the reliability and dependability of systems that handle legal proceeding and decisions while still being straightforward enough to support new users seamlessly.