Document #:  DEV18OCA03


Question:   Battelle requests an extension to the March 12, 2018 due date for applications to Ohio Coal Demonstration and Pilot Program Request for Proposals (RFP) Number: DEV18OCA03. We request the deadline be extended to April 30, 2018. Battelle anticipates two RFPs to be issued by the U.S. Department of Energy (U.S. DOE) to be considered for match funding by this OCDO RFP. The relevant RFP topics include: geomechanics and regional geological analysis. Once issued, Battelle plans to submit proposals to both RFPs, and apply for match funding by OCDO.

Answer:   Although ODSA encourages applicants to leverage federal funding sources, state appropriation authority timelines cannot accommodate this request. Full proposals continue to be due by March 12, 2018.

Date: 3/5/2018

Inquiry: 52508


Question:   Battelle requests an extension to the March 12, 2018 due date for applications to Ohio Coal Demonstration and Pilot Program Request for Proposals (RFP) Number: DEV18OCA03. We request the deadline be extended to April 30, 2018. Battelle anticipates two RFPs to be issued by the U.S. Department of Energy (U.S. DOE) to be considered for match funding by this OCDO RFP. The relevant RFP topics include: geomechanics and regional geological analysis. Once issued, Battelle plans to submit proposals to both RFPs, and apply for match funding by OCDO.

Answer:   Although ODSA encourages applicants to leverage federal funding sources, state appropriation authority timelines cannot accommodate this request. Full proposals continue to be due by March 12, 2018.

Date: 3/5/2018

Inquiry: 52507


Question:   I got the following questions from the faculty member Im working with: QUESTIONS #1: Regarding the Audit, DO you imply that we have to attach the latest version of the Audit (103 pages) ? QUESTIONS #2: Can I include the full Audit (103 pages) only in the original version of the proposal, and for the additional copies I have only the first page of the Audit ?

Answer:   Q1: Regarding the Audit, DO you imply that we have to attach the latest version of the Audit (103 pages)? A1: Applicants will need to attach the latest and full version of the audit. Applicants must include a copy of their audit electronically as either a pdf or word document. If the latest and full audit is available online, the listing of an active weblink will also be accepted in lieu of a pdf or word document. Q2: Can I include the full Audit (103 pages) only in the original version of the proposal, and for the additional copies I have only the first page of the Audit? A2: The RFP states on page 16, that “only one (1) copy of each audit needs to be included.” The full audit must be included.

Date: 2/26/2018

Inquiry: 51368