Opportunity Detail

Questions and Answers

ORPHAN WELL - OIL AND GAS WELL PLUGGING PROJECTS
Document #:  CSP907118


Question:   On Page 7 of the RFP, the text states "Each Offeror must submit one (1) original, completed and signed in blue ink, and five (5) copies for a total of six (6) Proposal packages. The Offeror must also submit, in the sealed package, a complete copy of the Proposals on CD-ROM in Microsoft Office (Word, Excel, or Project) 2003 or higher, format and/or PDF format as appropriate." On Page 18 of the RFP, the text states "1.7 NUMBER OF PROPOSALS TO SUBMIT Offeror must submit one (1) original, completed and signed in blue ink, and four (4) copies for a total of five (5) Proposal packages. Additionally, Offeror shall submit two (2) electronic copies of the Proposal package on USB memory sticks." Could you please clarify if either (or both) electronic formats are required for proposal submission? The two statements also conflict as to how many total copies of the proposal are required.

Answer:   Q:51074 A:DAS Responds: PROPOSAL SUBMITTAL. Each Offeror must submit one (1) original, completed and signed in blue ink, and five (5) copies for a total of six (6) Proposal packages. The Offeror must also submit, in the sealed package, a complete copy of the Proposals on CD-ROM in Microsoft Office (Word, Excel, or Project) 2003 or higher, format and/or PDF format as appropriate.

Date: 2/5/2018

Inquiry: 51074


Question:   Will the 13 5/8 conductor be pulled pryor to cementing the 8 5/8 surface casing? Attachment Ten: Hypothetical Site Specific Orphan Well Scope of Work Page 76 - Conductor

Answer:   Q:51068:A:DAS Responds: This question dictates Contractor means and methods. DAS cannot dictate means and methods to contractors. A scenario such as this would be discussed and agreed upon between DNR and Contractor staff based on the situation and circumstances.

Date: 2/5/2018

Inquiry: 51068


Question:   Bonding will be required on an actual contract. Do you want bonding costs included in the hypothetical bid? Attachment Ten: Hypothetical Site Specific Orphan Well Scope of Work Part 8: Project Bond Page 64

Answer:   Q:51067: A:DAS Responds: No, bonding will not be included in the hypothetical bid.

Date: 2/5/2018

Inquiry: 51067


Question:   I understood that during fishing and milling that ODNR would supply appropriate mills or fishing tools. What about the bits necessary for clean out of the well bore? Are the contractors responsible for supplying those? Supplement One Page 60

Answer:   Q:51066:A:DAS Responds:The Division does not physically supply any tools for the work. The Division has Detailed Specifications and Contingency Line items to pay for work whenever things such as milling or fishing are required. This would include the contractor supplying all the equipment and labor to mill or fish with the exception the that Division will negotiate a change order to address the cost of any special milling bits or fishing tools that are required for the specific circumstances encountered. These details described here are further described in the Detailed Specifications.

Date: 2/5/2018

Inquiry: 51066


Question:   In the example project, it is stated that ODNR will obtain all necessary USACE permits. Does ODNR intend to handle all of the environmental/ecological permitting and coordination using its own staff, or will it be the responsibility of the contractor?

Answer:   Q:49994:A:DAS Responds: The permitting and coordination for all environmental/ecological requirements will not be the supplier of this contracts responsibility. These conditions will either be met by ODNR staff or a separate supplier already on contract.

Date: 1/29/2018

Inquiry: 49994


Question:   Do you need to bid on every project or can you bid on those that are convenient to your location?

Answer:   Q:49992:A:DAS Responds:If you pass the proposal process you are added as a supplier on the contract and you can bid on any projects you wish that are posted on the DNR website.

Date: 1/29/2018

Inquiry: 49992


Question:   Is there an environmental component to this RFP? E.g. some of our oil and gas clients ask us to do environmental screening of P & A sites prior to the performance of any site activities. Beth Ullom, Environmental Lead, Enercon Pittsburgh

Answer:   Q:49921:A:DAS Responds: Environmental site reviews of orphan well sites are conducted by the ODNR Division of Oil and Gas Resources Management. The project specific Scope of Work for each individual project details the environmental considerations.

Date: 1/29/2018

Inquiry: 49921


back

Inquiry period ended:  2/5/2018 8:00:00 AM